There is both British Standard
and European Regulation to ensure that plant is comprehensively
tested. Where we are engaged to provide a fully detailed specification
and /or we undertake the management of a project we strictly
enforce our witnessing of the regulatory tests undertaken
by the Contractor. The results of the exercise are compared
with the parameters and readings established by the Contractor,
subsequent to which our findings are formally certified for
issue to Clients (may be necessary for insurance purposes)
on the prescriptive forms. In sequence with witness testing
a formal schedule of defects (if any ) will be issued for
action as appropriate by the Contractor. |
|